What about SCHEDULE DANGLERS?

Open ends are great indicators of missing scope/s, incomplete and/or missing planning inputs. The solution is to tie all valid network activities in the right sequence, according to the approved project execution plan and path of construction.
A good schedule is a well-tied schedule and a well-tied schedule signifies complete scope.
Source: Frago, R. (2015/2017).Plan to Schedule, Schedule to Plan.ISBN 978-0-9947608-2-1.Canada.

A recent query from a colleague inspired me to write this short article on the subject of danglers, i.e. schedule danglers. I hope my humble insights will be useful.

Open start danglers are activities where the only predecessor is either Finish-to-Finish or Start-to-Finish, resulting in an open start to the activity. They are also known as “dangling activities.”

The number of activities with open start (danglers) should be zero.

The project scheduler should use Start-to-Start and Start-to-Finish links sparingly. Tie each activity end completely and properly to avoid danglers.

Read the full article by clicking the hyperlinked button below.

Continue Reading →

Effective P6 Administration by Improving Primavera Security through Correct Management of the Responsible Manager Code (RMC)

Project’s request to restrict access of other Users to their project schedules & portfolios seemed to have failed. Unauthorized access remains a problem. Contractors working concurrently in the same database were able to sometime see the client’s schedule and modified certain critical attributes despite the security protocol being enforced. Worst of all, one schedule was completely deleted by someone and have to be recovered from the back-end by the Database Administrator through the existing back-up and recovery protocol.

Dorothy was checking Marco’s security access because he couldn’t add resources and found that all his projects have the Responsible Manager’s Code set to the Contractor’s OBS code. She figured that Marco might have used the contractor’s original schedule as a starting project file in developing his project schedule.

Back in June 2010, Primavera User John and Mark had put together a schedule that sat on the back burner while the Project team worked on other priorities. When it came time to set the baseline, John and Mark decided to do a quick check to make sure nothing had changed. Mark hit the F9 button and about 80% of the activities moved to the right. The dates moved by 4 to 20 days.

The two of them checked the calendar they were using but they were fine. The Primavera database Administrator checked who else was using the calendar and the schedule and found that only John and Mark were given direct access to this schedule.

John now went back to the schedule, changed some lags and logics trying to correct the schedule discrepancies. The effort took more than a day to complete, time which the project really do not have. What has gone wrong?

Find out what happened. Read the full article by clicking the hyperlinked button below.

Continue Reading →

Tips to Effective Project Schedule Updates Part 2

The client company, through its representative, must review and give feedbacks to the contractor after receiving the schedule update/report. It is not only an expected feedback and input mechanism but also a responsibility.

Return inputs (feedbacks) must be in a timely, coordinated, and agreed-to manner so nothing goes between the cracks. All inputs and feedbacks shall be in writing via e-mail or handwritten correspondences.

Address the comments from the client in a formal construction meeting or documented informally, prior to such meeting. Engaging face to face is preferred to a teleconference call or remote engagement whenever possible.

Continue Reading →

FREE WHITE PAPER NO.6 : Ten Cardinal Rules to Good Schedule Baseline Management

A project that does not have a clear understanding on how to manage schedule baselines cannot expect to manage time…

Continue Reading →