Typical Attributes of a Phantom Schedule

Some of the typical attributes of a Phantom Schedule are as follow:

1) Secret (unknown to the other contracting party)

2) It is a simplified version of the contract schedule

3) Considered more reliable and accurate

4) Viewed as a validation schedule that provides better forecasts5.

5) Updated in the background by sponsoring party

6) Decision-making tool by sponsoring party. Management decisions are no longer based on the forecast of the current contract schedule.

Read more… know more!

Continue Reading →

How about understanding your Project’s Schedule Critical Path better?

Critical Path is a measure of schedule flexibility, discernable through each activity total float. On any network path, flexibility is the positive difference between early and late dates (PMI, Project Risk Management, 2013). It is the shortest time possible for a project to finish.

“Be careful of relative critical path. This is the critical path relative to some select points of constraint only.”

“The path it generates does not represent the overall project’s critical path. The real overall critical path of the schedule is one generated by the calculation of a schedule that has no constraint, a schedule that flows freely.

Continue Reading →